A Resolution Amending The Scope Of Work And Budget Within
Meadow Lakes Road Service Area No. 27, To Reallocate Funds
From West Swan Drive And South Rainbow Street Improvements To
Herkimer Drive And Spring Drive Improvements.
2. ACTION MEMORANDUMS
Award Of Bid No. 26-137B To Northern Asphalt Construction, Inc.
In The Amount Of $292,352 To Construct East Knik View Drive
And South Knik Circle Street Improvements.
Award Of Bid No. 26-142B AK Clearwater Mechanical, LLC. In
Contract Amount Of $123,441 For The Colony Middle School
Boiler Pump Upgrades.
Authorization To Renew The Borough’s Enterprise Tax And
Assessment Software With Tyler Technologies Under A Three-Year
Agreement Covering July 1, 2026, Through June 30, 2029, With
Annual Payments Averaging $416,095 Subject To Appropriation.
Authorization To Renew The Borough’s Microsoft Enterprise
Agreement With Crayon Software Experts, LLC. Under A
Three-Year Agreement Covering July 1, 2026, Through June 30,
2029, With Annual Payments Of $476,979.91 Subject To
Appropriation.
Authorization To Renew The Borough’s GIS Software And Services
With Environmental Systems Research Institute, Inc. Under A
Three-Year Agreement Covering July 1, 2026, Through June 30,
2029, With Annual Payments Averaging $303,936 Subject To
Appropriation.
Authorization To Renew Palo Alto Software And Hardware With
World Wide Technology Inc. Under A Three-Year Agreement
Covering July 1, 2026, Through June 30, 2029. The Total Cost Of
The Agreement Is $258,937.41 With Annual Payments Subject To
Appropriation.
Approval Of Change Order No. Two For Contract No. 25-124P With
PND Engineers, Inc. For The Wolf And Hart Lakes Drainage Study
And Improvements Design Project To Add $229,230 For Design
Services; And Extend The Completion Date To December 31, 2028.