Skip to main content
Matanuska Banner
File #: AM 25-127    Version: 1 Name:
Type: Action Memo Status: Consent Agenda - AM
File created: 10/7/2025 In control: ASSEMBLY REGULAR MEETING
On agenda: 10/21/2025 Final action:
Title: Approval Of Utility Relocation Costs Of $194,560.55 To MTA Communications, LLC. For The Fern Street Upgrade And Pathway Project Within The City Of Wasilla; And To Extend The Completion Date To October 31, 2026.
Attachments: 1. AM 25-127
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

Approval Of Utility Relocation Costs Of $194,560.55 To MTA Communications, LLC. For The Fern Street Upgrade And Pathway Project Within The City Of Wasilla; And To Extend The Completion Date To October 31, 2026.