Matanuska Banner
File #: AM 19-107    Version: 1 Name:
Type: Action Memo Status: Passed
File created: 9/10/2019 In control: ASSEMBLY REGULAR MEETING
On agenda: 11/19/2019 Final action: 11/19/2019
Title: Approval Of Contract Amendment No. 1 To Contract No. 18-100B With Orion Marine Contractors, Inc. In The Amount Of $94,763.48 For Port Mackenzie Dock Repairs, Phase II, Project No. 70012, To Modify The Tasks, Resolve The Contractor’s Additional Work Claim, And Report The Conclusion Of The Contract For The Final Contract Amount Of $2,140,826.48.
Attachments: 1. 2019-AM-107

Title

Approval Of Contract Amendment No. 1 To Contract No. 18-100B With Orion Marine Contractors, Inc. In The Amount Of $94,763.48 For Port Mackenzie Dock Repairs, Phase II, Project No. 70012, To Modify The Tasks, Resolve The Contractor’s Additional Work Claim, And Report The Conclusion Of The Contract For The Final Contract Amount Of $2,140,826.48.